Contracts
A construction contract includes a liquidated-damages clause of $5,000 per day of delay on a project where the actual daily delay loss is easily calculated at $200. Under O.C.G.A. § 13-6-7 and Southeastern Land Fund v. Real Estate World, the clause most likely: