Florida Board Rejects Settlement for Modern Lux Pools Qualifier, Counters at Double

Florida's CILB rejected a $2,500 settlement for Modern Lux Pools qualifier Lexander Acosta on Nov. 12, 2026 and countered at $5,000. The 489.129 rules the exam tests.

By 9 MIN READ

On November 12, 2026, Florida's Construction Industry Licensing Board (CILB) unanimously rejected a proposed settlement that would have cost the former qualifier for Modern Lux Pools a $2,500 fine, one year of probation, and 14 hours of continuing education. The board doubled every term in a counteroffer and put revocation on the table if he refuses it.

If you are studying for the Florida Business and Finance exam, this case tests three things at once: what a qualifying agent is responsible for under Section 489.1195, the abandonment grounds and penalty menu in Section 489.129, and the difference between a county board revoking local permit privileges and the state board acting on the license itself.

This is an independent study aid, not affiliated with the DBPR, the Construction Industry Licensing Board, or Pearson VUE. It is a study summary, not legal advice. Board discipline proceedings are administrative actions on a license. No criminal charge against Acosta arising from the Modern Lux Pools projects has been reported in the coverage verified for this post.

01What happened

Per WINK Investigates (Chorus Nylander, November 12, 2026), reporting on the CILB meeting in Safety Harbor, Florida, and the Naples News Now summary (November 4, 2026) of WINK's October 29, 2026 reporting on the county hearing:

  • Lexander Acosta was the qualifying agent for Modern Lux Pools, a Southwest Florida pool contractor, when the projects at issue were undertaken. WINK describes him as the company's former qualified license holder.
  • On October 21, 2026, the Collier County Contractor's Licensing Board voted unanimously to revoke Acosta's local permit-pulling privileges in Collier County indefinitely. County investigators found 17 of the 18 building permits pulled under Acosta for Modern Lux Pools had been abandoned or terminated since early 2024. The county board found willful building code violations, including concealing work that had not been inspected and starting construction without required permits. Acosta did not appear at the county hearing.
  • The county action does not, by itself, revoke a statewide contractor license. Collier County forwarded its findings to the Department of Business and Professional Regulation (DBPR). At the time of the October reporting, the state had 11 open cases involving Acosta's license, and a state hearing was expected in November.
  • On November 12, 2026, DBPR presented a proposed settlement to the CILB: a $2,500 fine, one year of probation, and 14 hours of continuing education. DBPR staff said the fines were low because another case against Acosta, involving another construction company, is still pending.
  • The board rejected the settlement unanimously. One member said he favored revoking the license outright. The board countered with a $5,000 fine, two years of probation, and 28 hours of continuing education. If Acosta does not accept the counteroffer, the case goes to a formal hearing, where the board will decide whether to revoke his license.
  • WINK cites a state document reporting at least 12 complaints filed against Acosta since 2024, with about $350,000 in damages. WINK's own investigation, begun in September 2026, found at least 30 homeowners reporting unfinished pool projects and about 30 lawsuits filed against the company. The company is accused of abandoning at least 11 projects.
  • Homeowner figures reported by WINK: Joe Grasso paid $150,000 of a $162,000 contract and his pool is not finished. A Cape Coral homeowner paid $42,000 for an unfinished project. Naples News Now reported one homeowner paid $76,000 for a pool that was never permitted, and another paid $52,500 and was left with an unfinished concrete structure.
  • Acosta told Grasso in a June text that he was no longer with the company and that "I was just the qualifier." Modern Lux Pools told WINK that Acosta was the qualifying contractor responsible for permitting and supervision, and said in a written statement that it supports a thorough, fair, and fact-based review of the complaints.

The November 12 article does not state a license number or license classification for Acosta. Do not add one to this case.

02"I was just the qualifier" is not a defense: 489.1195

Section 489.1195(1)(a) sets the primary qualifying agent's responsibility. All primary qualifying agents for a business organization are:

  • Jointly and equally responsible for supervision of all operations of the business organization.
  • Responsible for all field work at all sites.
  • Responsible for financial matters, both for the organization in general and for each specific job.

That is the rule this fact pattern tests. A primary qualifier cannot narrow the job to lending the license and pulling permits while someone else runs the work and the money.

Contrast the secondary qualifying agent under 489.1195(1)(e). A secondary qualifier is responsible only for supervision of field work at sites where his or her license was used to obtain the building permit, plus any other work he or she accepts responsibility for. A secondary qualifying agent is not responsible for supervision of financial matters. Exam questions swap primary and secondary on exactly this point.

One more distinction: if the board has approved a financially responsible officer for the business, the officer carries the financial aspects and the primary qualifying agent is responsible for all construction activities. No financially responsible officer arrangement has been reported in this case.

03The discipline menu and the abandonment grounds: 489.129

Section 489.129(1) lists what the board may impose on a certificateholder or registrant found guilty of a listed act:

  • Probation or reprimand.
  • Revocation, suspension, or denial of issuance or renewal.
  • Financial restitution to a consumer for financial harm directly related to a violation.
  • An administrative fine not to exceed $10,000 per violation.
  • Continuing education.
  • Costs of investigation and prosecution.

Both dollar figures in this case sit under that cap. The proposed $2,500 fine and the board's $5,000 counteroffer are each below the $10,000 maximum for a single violation. The cap is per violation, so a case built from many complaints is not capped at $10,000 in total.

The grounds the exam tests on these facts:

  • Abandonment, 489.129(1)(j): abandoning a construction project the contractor is engaged in or under contract for. A project may be presumed abandoned after 90 days if the contractor terminates without just cause or without proper notification to the owner, including the reason, or fails to perform work without just cause for 90 consecutive days.
  • Abandonment with excess payment, 489.129(1)(g)2: the contractor has abandoned a customer's job and the percentage of completion is less than the percentage of the total contract price paid, unless the contractor is entitled to retain the funds under the contract or refunds the excess funds within 30 days after the date the job is abandoned.
  • County discipline as a state ground: 489.129(1) also lists being disciplined by a municipality or county for an act or violation of this part as a ground for board discipline. The Collier County revocation of permit privileges is therefore not just background. It is itself a listed ground the state board can act on.

04A rejected stipulation is not the end of the case

The procedural point is the freshest part of this story, and it is testable. DBPR prosecutes the case and can present a negotiated settlement, called a stipulation, to the board. The board is not required to accept it. Here the board:

  1. Rejected the stipulation unanimously.
  2. Countered at double every term: $5,000 instead of $2,500, two years of probation instead of one, 28 hours of continuing education instead of 14.
  3. Left the licensee a choice: accept the counteroffer, or go to a formal hearing where revocation is the possible outcome.

A settlement offer from the department is a proposal until the board adopts it. Do not read a proposed fine in a news report as the final order.

05County action and state action are different licenses problems

Collier County revoked Acosta's ability to pull permits in that county. That action is local and indefinite, and it stands on its own. It did not revoke his state license, and the county board could not order the pools finished or the homeowners repaid. The state license is the CILB's to act on, through DBPR, and that is the proceeding now heading toward a formal hearing.

Homeowner recovery runs on a third track. The Florida Homeowners' Construction Recovery Fund (Sections 489.141 and 489.143) is a last resort, paid only on actual damages tied to a final judgment, restitution order, or board final order, with the claim filed within one year after the conclusion of the judicial or administrative proceeding. Pool and spa contracting sits in Division II, where the caps for contracts entered on or after July 1, 2024 are $30,000 per claim and $600,000 in aggregate per license. The Division I and Division II split is covered in Florida contractor license classifications. Administrative discipline alone, with no qualifying final order or judgment, does not write a Recovery Fund check.

06Testable numbers to memorize

  • $2,500 / 1 year / 14 hours: the DBPR settlement the CILB rejected on November 12, 2026 (fine, probation, continuing education).
  • $5,000 / 2 years / 28 hours: the board's counteroffer, exactly double on all three terms.
  • $10,000 per violation: the maximum administrative fine under 489.129(1).
  • 90 days: the abandonment presumption period under 489.129(1)(j).
  • 30 days: the window to refund excess funds after abandoning a job under 489.129(1)(g)2.
  • 17 of 18: permits pulled under Acosta for Modern Lux Pools that Collier County investigators found abandoned or terminated since early 2024.
  • 12 complaints, about $350,000: complaints against Acosta since 2024 and the damages figure in the state document WINK cited.
  • $30,000 / $600,000: Recovery Fund Division II caps per claim and in aggregate for contracts on or after July 1, 2024.

07Quiz yourself

Qualifying agent responsibility, abandonment, and board discipline penalties are repeat Business and Finance topics. Test your recall with the free 12-question Florida practice test, and review the full licensing framework in Florida contractor license requirements.

08Sources

Ready to test yourself?

Take the free 12-question Florida Business and Finance practice quiz with explanations for every answer, or get the full 88-page study guide with 150 practice questions.